Once the Backfilling was complete, we then prepared for the concrete slab to be laid, and over a couple of days where we got some really fine weather we poured around 25m3 of concrete!
Once the Slab had a chance to dry out it there was no stopping us, the Kit arrived and was erected by a squad from Sips Industries. I was away on tour at the time and missed most of the action but we managed to get some pics. The Kit goes up and was completed within 7 days
The Story continues.... We are currently working inside battening out ready for first fix. Most of the windows and doors have been fitted and the roof has been battened out, sarking fitted and a second membrane been fitted ready for slates. Plumber starting soon, Electrician at planning stage.
|
|||||||